多做题,通过考试没问题!

IBM认证考试

睦霖题库>其他计算机考试>IBM认证考试

A customer is planning on establishing a Global Mirror between two Storwize V7000 storagearrays. The customer is planning to lease an IP WAN connection between sites for the tasks andis running a SAP (database) application on Oracle. Which of the following planning considerationsis most important?()

  • A、the distance between sites needs to be less than 100 kilometers
  • B、consistency groups should be created to maintain write order on the remote mirror
  • C、ensure sufficient bandwidth exists on the link based on average application workloads
  • D、ensuring a low round trip latency of less than 30ms on the WAN connection is required
正确答案:B
答案解析:
进入题库查看解析

微信扫一扫手机做题