多做题,通过考试没问题!

思科认证考试

睦霖题库>软件认证工程师考试>思科认证考试

Refer to the exhi bit. ROUTE.com is planning to implement load balancing for traffic between host on the 172.16.10.0/24 and 172.16.20./24 networks. You have been asked to review the implementation plan for this project. Which statement about the plan is true?()

  • A、It is complete as written.
  • B、It should include a task to configure multipath to equal a value of 2 on R1 and R4.
  • C、It should use a ping instead of a traceroute to validate that load balancing has been activated.
  • D、It should conta in a task that documents the changes made to the configurations.
正确答案:D
答案解析:
进入题库查看解析

微信扫一扫手机做题