Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.
- A、activity duration estimating, schedule developing, activity resource estimating
- B、activity resource estimating, activity duration estimating, schedule development
- C、schedule developing, activity resource estimating, activity duration estimating
- D、activity resource estimating, schedule developing, activity duration estimating
正确答案:B