Which statement is true regarding the creation of nested plans using Resource Manager?()
- A、 Only one nested subplan is allowed.
- B、 The plans can be nested up to four levels.
- C、 Resource Manager does not support nested plans.
- D、 Nested plans control only the degree of parallelism but not the CPU.
- E、 Each nested plan gets a proportion of the CPU resources assigned to its parent group.
正确答案:E
答案解析:有