On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
- A、time estimating
- B、cost estimating
- C、project planning
- D、schedule development
正确答案:C