You are a network administrator for your company. The design team provides you with the following list of requirements for server disaster recovery:   No more than two sets of tapes can be used to restore to the previous day.  A full backup of each server must be stored off-site.   A full backup of each server that is no more than one week old must be available on-site.  Backups must never run during business hours.   Tapes may be recalled from off-site storage only if the on-site tapes are corrupted or damaged. A full backup of all servers requires approximately 24 hours. Backing up all files that change during one week requires approximately 4 hours. Business hours for the company are Monday through Friday, from 6:00 A.M. to 10:00 P.M.  You need to provide a backup rotation plan that meets the design team’s requirements.   Which two actions should you include in your plan?()

  • A、 Perform a full normal backup for on-site storage on Friday night after business hours. Perform a full copy backup for off-site storage on Saturday night after the Friday backup is complete.
  • B、 Perform a full normal backup for on-site storage on Friday night after business hours. Perform another full normal backup for off-site storage on Saturday night after the Friday backup is complete.
  • C、 Perform a full copy backup for on-site storage on Friday night after business hours. Perform a full copy backup for off-site storage on Saturday night after the Friday backup is complete.
  • D、 Perform differential backups on Sunday, Monday, Tuesday, Wednesday, and Thursday nights after business hours.
  • E、 Perform incremental backups on Sunday, Monday, Tuesday, Wednesday, and Thursday nights after business hours.
  • F、 Perform incremental backups on Sunday, Tuesday, and Thursday nights after business hours. Perform differential backups on Monday and Wednesday nights after business hours.
正确答案:A,D
答案解析:
进入题库查看解析