Which design phase service component consists of developing a detailed, site-specific plan for implementing a new technology system or solution? Select exactly 1 answer(s) from the following:()。

  • A、Detailed Design Development
  • B、Systems Acceptance Test Plan Development
  • C、Staging Plan
  • D、Implementation Plan Development
  • E、Project Kick-off
正确答案:D
答案解析: