A customer wants to implement the following Blades in BladeCenter H:Two POWER Blades running IBM i partitions.Two POWER Blades running AIX and LinuxFour x86 Blades running Windows. Which of the following design consideration statements is correct?()

  • A、The Blades must use the same CIOv and CFFh expansion adapter types.
  • B、Two physical BladeCenter H chassis will be required. One for the POWER Blades, the other for the x86  Blades.
  • C、The x86 Blades and POWER Blades may use different expansion adapters provided the POWER Blades  are in bays 1-7 and the x86 Blades are in slots 8-14.
  • D、The x86 Blades and POWER Blades may use different expansion adapters, provided the corresponding I/O modules to Blade midplane connections are configured in the Advanced Management Module (AMM).
正确答案:A