In project management , a (73) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (74) ,budget and duration, linked by dependencies and scheduled events.

  • A、schedule
  • B、activity
  • C、plan
  • D、contractor
正确答案:A